The draft amends the General Part of the Environmental Code Act (Keskkonnaseadustiku üldosa seadus) and five other laws. Environmental permit procedures become tighter: a separate completeness check, extensions capped at 12 months, and rules for amending applications. It also removes cattle farming from the industrial emissions regime, updates environmental charge rules, and sets out in law whose names are published in the KOTKAS information system.

Changes and additions

  1. Completeness check of permit application

    The permit issuer assesses within 21 days whether the application has the required data and documents and no obstructive defects. It sets at least 14 days to fix defects and rechecks the corrected application within 14 days (21 if another authority's input is needed). If defects persist, it can leave the application unreviewed by a reasoned written decision.
  2. Start and suspension of the decision period; 12-month cap

    The period ran from receipt of a compliant application. Time spent fixing defects was not counted. Extensions had no overall cap.
    The period runs from the application being declared compliant and is suspended while an obstructive defect is fixed. Extensions are allowed, but the decision must come within 12 months of that declaration, excluding suspension time. The refusal period in § 49(3) rises from 20 to 30 days.
  3. Amending an application during the procedure

    The applicant submits a description of the change. The permit issuer decides within 14 days whether it can be handled in the ongoing procedure, and the deadline is suspended meanwhile. If not, the applicant chooses to continue unchanged or file a new application; the earlier one is deemed withdrawn only if the new one is filed in time. Separate new applications are assessed separately and may be merged with the applicant's consent.
  4. Early and consolidated remarks on defects

    The permit procedure must be organised so that essential facts are established as early as possible and remarks on defects are given together, except when new essential facts arise.
  5. Safeguards when a permit is amended

    The permit issuer sets a reasonable period for meeting a new or stricter obligation, unless a deadline is already set by law. The permit holder is informed if other conditions need changing, and at their request these are handled in a separate procedure.
  6. Publication of natural persons' names in KOTKAS

    The law lists whose names are published (applicants and holders, procedure participants, report submitters, developers and experts of environmental impact assessments and strategic environmental assessments) and for how long. Only the name is published. The basic regulation may shorten, but not lengthen, the periods.
  7. Cattle farming leaves the industrial emissions law

    Cattle farming was an activity requiring an integrated (complex) permit, with a reduced inspection frequency exception.
    Cattle farming is removed from the Industrial Emissions Act (Tööstusheite seadus) and the State Fees Act (Riigilõivuseadus). Existing complex permits are reissued as environmental permits within four years without an open procedure. Pending applications continue as environmental permit procedures, and fees paid in excess are refunded.
  8. Environmental charges: electronic filing, marine pollution, refunds

    Declarations could be filed by post, on electronic media, by electronic data transfer or in person. For oil discharges, the Environmental Board (Keskkonnaamet) needed a declaration. A deforestation fee refund could be requested within two years, and the wind-power fee cap was not tied to a date.
    Declarations are filed via the KOTKAS information system, with exceptions on reasoned request. The Environmental Board may set the fee for oil discharges to the sea directly by notice. The refund deadline for the deforestation right fee is cut to one year. The wind-power fee cap uses the minimum wage in force on 1 March of the payout year. Some provisions apply from 1 October 2027.